Farming companies are becoming more and more standardized, not only for environmental protection easily, but also to generate some additional "income" for their own companies. This is due to the fact that the excrement of the breeding plant is composted through harmless treatment, which not only significantly improves the natural environment of the internal structure of the plant, but also allows it to be marketed as "organic fertilizer" in the sales market. Through the selection of residues, alcohol compost, plus light fertilizer deep processing into high-quality fertilizer, a ton can be sold to 600 yuan or even on the 1000 yuan.
How to install organic fertilizer production and processing equipment after the purchase? Sand machinery and equipment as a specialized fertilizer equipment production manufacturers, with more than ten years of production work experience, today, but more than the superfluous equipment, the key to tell you about organic fertilizer equipment installation: organic fertilizer production line equipment installation process.
Organic Fertilizer Production Line Equipment Installation Process Introduction1, Installation before the organic fertilizer production equipment according to the general plan and road base map, check the installation of the basic specifications are not to meet the provisions of the drawings, if there is not in line with the place, should carry out maintenance, until the specifications are appropriate, and then carry out the installation.
2, Installation staff should first understand the provisions of the installation of organic fertilizer production equipment, strictly in accordance with technical standards to carry out engineering construction.
3, Organic fertilizer production equipment in the delivery process may cause deformation, damage or loss, so before installation, to compare the equipment statistics, verification and acceptance of the project, and take effective countermeasures to make the equipment intact, and then carry out installation.
4, Each organic fertilizer production equipment into the installation site before the number to develop the installation process card and schedule, according to the provisions of the installation and processing process order, the equipment will be added to the site to carry out installation one by one.
5, Installation order: from top to bottom, first the server equipment and sound card rack position, and then install each articulated pipeline and household electrical equipment.
6, The installation of special tools required: organic fertilizer production and processing equipment and raw materials must be complete.
7, After the installation of organic fertilizer production equipment each rotating part, must rotate handy, no card, touch and knocking sound, each coupling parts must be solid, hermeticity, no leakage of manure, leakage of steam, oil seepage and other conditions.
8, The installation of household electrical equipment, should meet the relevant requirements, each line should be clear, there must not be running electricity, walking electricity condition, cable lines, cables should have maintenance housing, to avoid rat chewing rotten.
9, All equipment installation is completed, each single version should be carried out empty open test run, run normal can be funded into the load test run.
10, Before the load test run, the electronic device batching scales and package scales to carry out calibration, the provisions to achieve the required precision.
11, Load run 8h, no problem before handing over to the manufacturer production applications.
The above is the organic fertilizer production line equipment installation process is introduced, to recognize a large number of organic fertilizer equipment installation: organic fertilizer production line equipment installation steps in detail, warmly welcome to call Sande Machinery, customer service manager will explain in detail for you.